MUNROE CONCRETE
This expansion to Munroe concrete was a new expansion to the existing facilities that housed a 300 ft crane runway and new state of the art equipment. Stampa Steel Erectors Ltd. was tasked with the installation of structural steel and crane runway support framing erected and completed within a tight 2 week schedule.
Project Highlights:
- In order to meet the clients tight schedule a day & night shift was used to successfully complete the building envelope within 2 weeks.
- Close cooperation/planning with our clients ensured the projects success.
Date:
2011General Contractor:
Munroe ConcreteSteel Fabricator:
Benson Steel Ltd.Approx. Tonnage:
360 tonsLocation:
Barrie, Ont.Category:
Date:
December 3, 2021